The planned MRT Jakarta East-West Line is one of the most significant developments for eastern Jakarta and Bekasi. The line's eastern end is planned at Medan Satria, the area where Kota Harapan Indah is located, connecting Bekasi directly to the MRT Jakarta network for the first time.
This article summarises the latest facts on the route, stations, construction timeline, and the transit-oriented development (TOD) plan in Medan Satria, based on information published by PT MRT Jakarta (Perseroda) and Damai Putra Group.
The East-West Line is planned to run from Cikarang in West Java to Balaraja in Banten, crossing three provinces. Construction is divided into several stages:
Phase 1 Stage 1: Tomang to Medan Satria, 24.5 km with 21 stations, plus a 5.9 km access line to the Rorotan depot
Phase 1 Stage 2: Tomang to Kembangan, 9.2 km
Phase 2: Kembangan to Balaraja, and Medan Satria to Cikarang
This means Medan Satria is the eastern terminus of the very first construction stage. Kota Harapan Indah does not need to wait for later phases to be connected to the MRT.
Based on plans published in 2024, the Tomang to Medan Satria line will serve the following 21 stations:
Tomang, Grogol, Roxy, Petojo, Cideng, Thamrin, Kebon Sirih, Kwitang, Senen, Galur, Cempaka Baru, Sumur Batu, Pakulonan Barat, Pakulonan Timur, Perintis, Pulogadung, Penggilingan, Cakung Barat, Pulo Gebang, Ujung Menteng, and Medan Satria.
A key station on this line is Thamrin Station, designed as the interchange between the North-South and East-West lines. Passengers from Medan Satria will be able to transfer to the line serving Sudirman, Senayan, and Lebak Bulus.
The line combines elevated and underground sections, with 13 elevated stations and 8 underground stations. Station names and numbers may still change as planning progresses.
PT MRT Jakarta has stated that construction of Phase 1 Stage 1 is targeted to begin in late 2026, following a tender process in late 2025. Funding for this stage is supported by loans from the Japan International Cooperation Agency (JICA) and the Asian Development Bank (ADB).
In 2024, PT MRT Jakarta announced a completion target of 2031 for the Tomang to Medan Satria line, with a projected capacity of around 284,000 passengers per day. This target may be adjusted as the project progresses.
In November 2025, Damai Putra Group and PT MRT Jakarta signed a memorandum of understanding (MoU) to explore a Transit Oriented Development (TOD) in Medan Satria, Kota Harapan Indah. Read more in the article Damai Putra Group and MRT Jakarta Sign MoU on Medan Satria TOD Development.
The TOD is envisioned as more than a passenger stop. The concept being explored includes direct integration with the MRT station, retail and F&B areas, public spaces, and comfortable, accessible pedestrian walkways, creating a new centre of activity in eastern Jakarta.
According to Lenny Wijaya, Damai Putra Group, the collaboration is a strategic step toward building a more modern transit-oriented ecosystem in Kota Harapan Indah, while strengthening the township's role as a future-ready city.
The MRT will add a new transport option for residents who work or study in Jakarta. Until now, travel from eastern Bekasi to the city centre has relied heavily on toll roads and commuter rail. With the MRT, journeys to areas such as Pulogadung, Senen, and Thamrin can be made on high-capacity rail that is unaffected by road congestion.
While the MRT is being built, Kota Harapan Indah is already connected to nearby toll roads, commuter rail, and Transjakarta services, and offers city-scale facilities such as BPK Penabur and Al Azhar schools, Hotel Santika Premiere Kota Harapan Indah, and a university.
If you are considering a home in the area, Damai Putra Group currently offers three clusters starting from IDR 1 billion: CRESTA, HOSHI, and ALBASIA. See the full comparison in Kota Harapan Indah House Prices 2026: Comparing CRESTA, HOSHI, and ALBASIA.
Will the MRT reach Kota Harapan Indah?
Yes. Phase 1 Stage 1 of the East-West Line is planned to run from Tomang to Medan Satria, the area where Kota Harapan Indah is located.
When will East-West MRT construction begin?
PT MRT Jakarta is targeting the start of Phase 1 Stage 1 construction in late 2026.
When will the Tomang to Medan Satria MRT open?
In 2024, PT MRT Jakarta announced a completion target of 2031. This target may change as the project progresses.
How many stations are there between Tomang and Medan Satria?
Based on published plans, there are 21 stations along 24.5 km, comprising 13 elevated and 8 underground stations.
What is the Medan Satria TOD?
The Medan Satria TOD is a transit-oriented development being explored by Damai Putra Group and PT MRT Jakarta under an MoU signed in November 2025, covering station integration, commercial areas, public spaces, and pedestrian walkways.
For more information about homes in Kota Harapan Indah, contact the Damai Putra Group Marketing Gallery via WhatsApp Official 0811 4466 888 or visit www.damaiputra.com.
This article summarises the latest facts on the route, stations, construction timeline, and the transit-oriented development (TOD) plan in Medan Satria, based on information published by PT MRT Jakarta (Perseroda) and Damai Putra Group.
The East-West MRT Route: From Tomang to Medan Satria
The East-West Line is planned to run from Cikarang in West Java to Balaraja in Banten, crossing three provinces. Construction is divided into several stages:
Phase 1 Stage 1: Tomang to Medan Satria, 24.5 km with 21 stations, plus a 5.9 km access line to the Rorotan depot
Phase 1 Stage 2: Tomang to Kembangan, 9.2 km
Phase 2: Kembangan to Balaraja, and Medan Satria to Cikarang
This means Medan Satria is the eastern terminus of the very first construction stage. Kota Harapan Indah does not need to wait for later phases to be connected to the MRT.
Phase 1 Stage 1 Stations
Based on plans published in 2024, the Tomang to Medan Satria line will serve the following 21 stations:
Tomang, Grogol, Roxy, Petojo, Cideng, Thamrin, Kebon Sirih, Kwitang, Senen, Galur, Cempaka Baru, Sumur Batu, Pakulonan Barat, Pakulonan Timur, Perintis, Pulogadung, Penggilingan, Cakung Barat, Pulo Gebang, Ujung Menteng, and Medan Satria.
A key station on this line is Thamrin Station, designed as the interchange between the North-South and East-West lines. Passengers from Medan Satria will be able to transfer to the line serving Sudirman, Senayan, and Lebak Bulus.
The line combines elevated and underground sections, with 13 elevated stations and 8 underground stations. Station names and numbers may still change as planning progresses.
East-West MRT Construction Timeline
PT MRT Jakarta has stated that construction of Phase 1 Stage 1 is targeted to begin in late 2026, following a tender process in late 2025. Funding for this stage is supported by loans from the Japan International Cooperation Agency (JICA) and the Asian Development Bank (ADB).
In 2024, PT MRT Jakarta announced a completion target of 2031 for the Tomang to Medan Satria line, with a projected capacity of around 284,000 passengers per day. This target may be adjusted as the project progresses.
Medan Satria TOD: A Collaboration Between Damai Putra Group and MRT Jakarta
In November 2025, Damai Putra Group and PT MRT Jakarta signed a memorandum of understanding (MoU) to explore a Transit Oriented Development (TOD) in Medan Satria, Kota Harapan Indah. Read more in the article Damai Putra Group and MRT Jakarta Sign MoU on Medan Satria TOD Development.
The TOD is envisioned as more than a passenger stop. The concept being explored includes direct integration with the MRT station, retail and F&B areas, public spaces, and comfortable, accessible pedestrian walkways, creating a new centre of activity in eastern Jakarta.
According to Lenny Wijaya, Damai Putra Group, the collaboration is a strategic step toward building a more modern transit-oriented ecosystem in Kota Harapan Indah, while strengthening the township's role as a future-ready city.
What Does This Mean for Kota Harapan Indah Residents?
The MRT will add a new transport option for residents who work or study in Jakarta. Until now, travel from eastern Bekasi to the city centre has relied heavily on toll roads and commuter rail. With the MRT, journeys to areas such as Pulogadung, Senen, and Thamrin can be made on high-capacity rail that is unaffected by road congestion.
While the MRT is being built, Kota Harapan Indah is already connected to nearby toll roads, commuter rail, and Transjakarta services, and offers city-scale facilities such as BPK Penabur and Al Azhar schools, Hotel Santika Premiere Kota Harapan Indah, and a university.
If you are considering a home in the area, Damai Putra Group currently offers three clusters starting from IDR 1 billion: CRESTA, HOSHI, and ALBASIA. See the full comparison in Kota Harapan Indah House Prices 2026: Comparing CRESTA, HOSHI, and ALBASIA.
Frequently Asked Questions
Will the MRT reach Kota Harapan Indah?
Yes. Phase 1 Stage 1 of the East-West Line is planned to run from Tomang to Medan Satria, the area where Kota Harapan Indah is located.
When will East-West MRT construction begin?
PT MRT Jakarta is targeting the start of Phase 1 Stage 1 construction in late 2026.
When will the Tomang to Medan Satria MRT open?
In 2024, PT MRT Jakarta announced a completion target of 2031. This target may change as the project progresses.
How many stations are there between Tomang and Medan Satria?
Based on published plans, there are 21 stations along 24.5 km, comprising 13 elevated and 8 underground stations.
What is the Medan Satria TOD?
The Medan Satria TOD is a transit-oriented development being explored by Damai Putra Group and PT MRT Jakarta under an MoU signed in November 2025, covering station integration, commercial areas, public spaces, and pedestrian walkways.
For more information about homes in Kota Harapan Indah, contact the Damai Putra Group Marketing Gallery via WhatsApp Official 0811 4466 888 or visit www.damaiputra.com.